Sometime in early December, the radios that Staunton’s police officers and firefighters carry will begin talking to a new network.
The city’s October 2026 activity report lists go-live for the SAW Regional Radio project, short for Staunton, Augusta and Waynesboro, as early December. Augusta County staff told supervisors on Oct. 26 that the cutover is tentatively targeted for the week of Dec. 7. We could not confirm a firm date for Staunton.
For most residents the switch will pass unnoticed. For the people who answer 911 calls, it is the largest equipment change in years.
Dead spots and phone calls
The old arrangement left holes in coverage. Kurt Plowman, Staunton’s chief technology officer and chair of the radio project, said the city has dead spots where fire and police radio transmissions fail, which forces dispatchers to reach personnel by phone, a problem he called a serious safety issue, the News Leader reported. He said the effort had been in the making for about eight years, and that neighboring jurisdictions such as Harrisonburg, Rockingham, Albemarle and Rockbridge had already moved to L3Harris systems over the past five or six years.
Gary Critzer, Waynesboro’s emergency management director, told the same outlet the three localities were due for upgrades and that moving together made economic sense. Each agency keeps its own talk groups, but all share the major infrastructure, which he said should improve interoperability and coverage across the region. The News Leader put the cost at about $15 million, divided among the three jurisdictions, with L3Harris of Lynchburg handling the work.
A schedule that has moved
The December target follows an earlier slip. When Plowman briefed Staunton’s Council in October 2025, he said the go-live had shifted from November to January so the contractor and staff could improve coverage. At that point more than 200 mobile radios had been installed, and the full system will use roughly 3,000. The city also ran vehicle-based coverage testing across the region in September 2025, its announcement said, to measure signal quality and confirm performance standards.
Coverage testing matters more in some seasons than others. Critzer said earlier that the work had to finish before the leaves fell, because foliage weakens signals, per the News Leader.
The last pieces
Two loose ends remain. In Augusta County, the permanent Mount Solon tower site will not be ready by the December cutover, so staff are preparing a temporary connection between the new and legacy systems to keep responders in that area talking. The county’s share of added project costs is estimated at about $180,000.
Training is the other. Staunton’s activity report says L3Harris has finished train-the-trainer sessions, and those trainers will now teach end users and provide support. Dispatch centers in all three jurisdictions get new consoles under the project’s agreement, according to the regional memorandum.
For people who listen in
Hobbyists who monitor public safety traffic should check their gear. The system is listed as a P25 Phase II network, per RadioReference, and older analog scanners cannot decode that format. We found no public statement on which channels will be open to listeners.
Source: City of Staunton, October 2026 Activity Report (released November 2026).